Summary:
The EI report of Changshouhua's "functional edible oil project" and the
EI report of Shandong Hongsheng's "pre-gelatinised starch products
& equipment upgrading project" were made public in early Feb. before
approval.
The
environmental impact (EI) report of Changshouhua Food Co., Ltd.
(Changshouhua)'s "200,000 t/a functional edible oil project" was
publicised on 8 Feb. by the local authority before approval.
Changshouhua
was founded in Nov. 2006 with a registered capital of RMB1.21 billion.
It is able to produce 300,000 t/a of corn oil. In order the meet the
diversified needs of consumers and find a new growth driver,
Changshouhua decided to launch this project.
Project overview:
Construction nature: New construction
Location: Handian Private Science and Technology Park, Zouping City (county-level), Binzhou City, Shandong Province
Total
investment: USD168.90 million (RMB1.2 billion), of which USD253,346
(RMB1.8 million) for environmental protection, accounting for 0.15%
Site area: 84,697 m2
Construction
content: Based on the existing idling workshop, build matching
utilities and supporting facilities and purchase a series of production
equipment
Labour quota: 156 new employees
Working system: Three 8hr shifts per workday, totalling 300 working days a year
Construction period: 12 months
Table Production capacity of functional edible oil project
Product
|
Production capacity, t/a
|
Main ingredient
|
Peanut oil
|
150,000
|
Peanut (purchased)
|
Diglyceride
|
25,000
|
Diglyceride-containing corn oil
|
25,000
|
Corn oil (purchased)
|
Source: Changshouhua
On
the same day, the EI report of Shandong Hongsheng Starch Technology
Co., Ltd. (Shandong Hongsheng)'s "50,000 t/a pre-gelatinised starch
products & equipment upgrading project" was publicised by the local
authority before approval.
Shandong
Hongsheng was established in April 2018 with a registered capital of
RMB10 million. This project is intended to upgrade the production
process and equipment for the existing project so as to meet the market
demand, improve product quality and reduce energy consumption as much as
possible.
Project overview:
Construction nature: Technological upgrading
Location: Zouping City (county-level), Binzhou City, Shandong Province
Total
investment: USD1.69 million (RMB12 million), of which USD168,898
(RMB1.2 million) for environmental protection, accounting for 10%
Site area: 5,300 m2
Construction content:
Convert the raw material warehouse into a liquid pre-gelatinised starch workshop
Add some production equipment
Consumption of main raw materials:
20,000 t/a of corn starch
11,282 t/a of cassava starch
1,500 t/a of hydroxypropyl cellulose
Labour quota: 10 employees
Working system: Three 8hr shifts per workday, totalling 300 working days a year
Construction period: 3 months
Table Shandong Hongsheng's production capacity
Product
|
Production capacity, t/a
|
Note
|
Current capacity
|
After upgrade
|
Liquid pre-gelatinised starch
|
30,000
|
45,000
|
Containing 80% water
|
Solid pre-gelatinised starch
|
20,000
|
5,000
|
Containing 10% water
|
Note: Total production capacity remains the same as before the upgrade.
Source: Shandong Hongsheng
Source:CCM
More information can be found at CCM Corn Products China Monthly Report.
About CCM:
CCM
is the leading market intelligence provider for China’s agriculture,
chemicals, food & feed and life science markets. Founded in 2001,
CCM offers a range of content solutions, from price and trade analysis
to industry newsletters and customized market research reports. CCM is a
brand of Kcomber Inc.
For
more information about CCM, please visit www.cnchemicals.com or get in
touch with us directly by emailing econtact@cnchemicals.com or calling
+86-20-37616606.